OVERVIEW

ECG Facilities Services were very pleased when our organisation was awarded the contract for the CWST Install and Associated Works at the West of Scotland Laundry facility in Wishaw on behalf of NHS Lanarkshire. ECG’s Projects Installation Team produced a formal programme of works which was submitted to NHS Lanarkshire for review and approval prior to any works being carried out. We adopted a phased approach due to the specific requirements of the facility due to works being carried out in a ‘live’ environment where it was crucial that the works were undertaken in a way which did not impinge production within the facility. ECG worked in close collaboration with NHS Lanarkshire’s key personnel to ensure all works were programmed at the most suitable times to ensure any disruption at the laundry facility was kept to an absolute minimum. As a result of operating within this partnership approach, all works were carried out on time, within budget and to the highest professional standards – much to the delight of NHS Lanarkshire.

BACKGROUND

With responsibility for improving the health and well-being of over half a million people, NHS Lanarkshire encompasses both the North and South Lanarkshire constituencies within the Central Belt of Scotland. University Hospital Monklands serves the local area with a 24-hour A&E department and has over 400 inpatient beds.

SERVICES DELIVERED

Strip out of existing CWST and associated redundant pipework
Supply and installation of new CWST, water filtration plant and associated pipework
Procurement, management and auditing of all associated specialist subcontractor services